Home » Marine Electrical Technology » Main Switch Board (MSB) Safeties, Protection and Maintenance
Main Switch Board (MSB) Safeties, Protection and Maintenance
- Main Switch Board or MSB to be installed on a raised platform.
- The location where Switch Board or MSB is installed should have good ventilation, illumination and affected by minimum vibration.
- No water or oil pipes should pass above the Switch Board or MSB.
- There should be adequate space around allowing comfortable operation ans maintenance.
- The operating floor space in front and behind the Switch Board or MSB should be covered with anti skid, insulated rubber mats with a minimum thickness of 15 mm.
- Panel doors should be in locked position.
- Door opening mechanism should be interlocked with power supply.
- The enclosure should be drip proof.
- MSB should be dead front type. (i.e. All the live conductor should pass behind MSB)
- Every equipment onboard must be properly earthed. Also MSB must be properly earthed.
- Every incoming and outgoing feed must be protected by a switch fuse or circuit breaker.
- Insulation resistance should not be less than 1 Mega Ohm in any case. Insulation Resistance (IR) to be checked and records are maintained.
- All meters must be calibrated periodically and records are maintained.
- All the meters, switches, fuses, push button, indicating lamps, etc. should be in working condition and identified with individual name plate or tag.
- All the interlocks must be in working condition.
- Operating switch gear, tools such as circuit breaker handle, fuse puller, lamp grip, etc. must be readily available and to be used.
- Red tag / name plate indicating high voltage and danger sign should be fitted
- Appropriate ready to use fire extinguishers should be positioned nearby. (CO2and DCP)
- Charts indicating drill procedures in case of electric shocks must be displayed near MSB.
- Wiring diagram laminated or framed indicating supply system must be displayed nearby.
- All the appropriate spares should be properly preserved and protected, individually packed and identified, and should be readily available for use.
- Earth fault indication should be fitted and displayed in front panel.
- 24 volt battery supply emergency light should be provided near MSB.
Related Posts
- May 24, 2014 Construction of a Main Switch Board (MSB) used in Ships
- March 31, 2015 Water Mist Fire Fighting System
- November 16, 2015 Stability of Ships During Dry Docking – Marine Engineering
- November 1, 2015 Crankcase Explosion on Ships – Marine Engineering
- October 1, 2015 Working and Maintenance of Air Ejector, Pressure Switch and Level Switch
- November 27, 2015 Cross Head Bearing Survey on Ships – Marine Engineering
- May 2, 2014 Internal Corrosion and Feed Water Treatment in Marine Boilers
- April 23, 2015 Testing of Water Mist Fire Fighting System onboard Ships
- May 2, 2014 Oily Water Separator or Bilge Oil Separator
- May 1, 2014 Explosimeter Working Principle
Very interesting
Looking forward to get more information on preparation with my orals class 1 engineer
good and simple
keep it up
Very good